This section explains the meta-release schedule and how to plan a meta-release.

Meta-release schedule

There are 2 CAMARA meta-releases per year: a Spring meta-release and a Fall meta-release. These are called SpringYY and FallYY respectively, where YY is the (short) year number.

  • A meta-release cycle covers 6 months between M0 and M6, including holidays.
  • The first CAMARA meta-release is Fall24, followed by Spring25, Fall25, etc.

The following figures provide the typical planning and milestone dates for a Spring or Fall meta-release.

Actual dates for a given meta-release can be found through the list of CAMARA meta-releases.

Spring meta-release plan


Fall meta-release roadmap


How to create a meta-release plan

For each meta-release, a meta-release plan shall be created that will plan and track the progress of the meta-release. It covers the status of

  • Commonalities and ICM releases
  • The API versions that are planned to be included in the meta-release.

To create the meta-release plan, the following steps shall be done: