Timeline

Fall meta-release scheduleM004/18M106/10M207/11M307/26M408/31M509/15M609/30Commonalities & ICMalpharelease-candidateAPI Sub Projectsalpharelease-candidateMeta-releasemeta-releaseretrospective

Milestone status

Milestone

Target dateStatusActual dateComment
M004-15 04-18

kick-off done

2024-04-18

 

M1 (Commonalities & ICM)04-30 05-15 05-31 06-15 06-10

Commonalities: alpha available

ICM: alpha / M1 skipped

2024-06-10

M1 was declared to be for Commonalities only by the TSC on 2024-07-04.

M2 (Commonalities & ICM)06-15 07-15 07-10

Commonalities: release PR ready

ICM: release PR ready

2024-07-11

Commonalities 0.4.0-rc.1 and ICM 0.2.0-rc.1 - approved on 2024-07-10.

M3 (Sub Projects)07-15 07-21 07-26preparation of first release-candidates by M3 (through one or more alpha API versions as needed)
Prepare your release PR by this date and have it reviewed by the Release Mgmt team before merging.
M4 (Sub Projects)08-30


M509-15


M609-30


Commonalities & ICM

This section is to be updated by the Commonalities and ICM working groups respectively.

Working GroupCommonalitiesICM

Target version

0.4.00.2.0

Target scope

Commonalities/issues/175IdentityAndConsentManagement/issues/146

M1 / date

2024-06-10

na

M2 / date

2024-07-112024-07-11

Pre-release tag

r0.4.0-rc.1v0.2.0-rc.1

M5 / date

yyyy-mm-ddyyyy-mm-dd
Public release tag<release tag link><release tag link>

API version release status

Below are the API release trackers of the API versions presented by the Sub Projects for this meta-release.

NOTE: API Sub Projects shall add their API release tracker latest by M3 when the meta-release content will be frozen.

In the below table, all data is automatically pulled from the API release trackers owned by the Sub Projects.

The individual API release tracker is the link in the first column called "API version".



API release contacts

API readiness checklist review (for use by RM team)

API list (for copying)