This page explains the meta-release schedule and how to plan a meta-release.

Meta-release schedule

There are 2 CAMARA meta-releases per year: a Spring release and a Fall release. These are called SpringYY and FallYY respectively, where YY is the (short) year number.

  • A meta-release cycle covers 6 months between M0 and M6, including holidays.
  • The first CAMARA meta-release is Fall24, followed by Spring25, Fall25, etc.

The following figures provide the planning and milestone dates for each meta-release. 

Spring meta-release plan

Fall meta-release roadmap

Create a meta-release planning page

For each meta-release, a meta-release planning page shall be created that show the progress of the meta-release. It covers:

  • Commonalities and ICM
  • all the API versions that are planned to be included in the meta-release.

To create the meta-release planning page, the following steps shall be done:

  • Go to the following page: Meta-release <meta-release name> and create a copy (under the CAMARA meta-releases parent page as indicated and keeping the images)
  • Follow the instructions in red on the copied page.