This page explains the meta-release schedule and how to plan a meta-release.
Meta-release schedule
There are 2 CAMARA meta-releases per year: a Spring release and a Fall release. These are called SpringYY and FallYY respectively, where YY is the (short) year number.
- A meta-release cycle covers 6 months between M0 and M6, including holidays.
- The first CAMARA meta-release is Fall24, followed by Spring25, Fall25, etc.
The following figures provide the planning and milestone dates for each meta-release.
Spring meta-release plan
Fall meta-release roadmap
Create a meta-release planning page
For each meta-release, a meta-release planning page shall be created that show the progress of the meta-release. It covers:
- Commonalities and ICM
- all the API versions that are planned to be included in the meta-release.
To create the meta-release planning page, the following steps shall be done:
- Go to the following page: Meta-release <meta-release name> and create a copy (under the CAMARA meta-releases parent page as indicated and keeping the images)
- Follow the instructions in red on the copied page.