Timeline
Milestone status
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 04-15 | kick-off done | 2024-04-18 |
|
M1 (Commonalities & ICM) | alpha | 2024-06-10 | r0.4.0-alpha.1 | |
M2 (Commonalities & ICM) | propose to shift by 1 month to 07-15 | |||
M3 (Sub Projects) | May be earlier :-) | |||
M4 (Sub Projects) | 08-30 | |||
M5 | 09-15 | |||
M6 | 09-30 |
...