Milestone

Target dateStatusActual dateComment
M004-15

kick-off done

 2024-04-18

 

M1 (Commonalities & ICM)04-30 05-15 05-31/ 06-15alpha PRfinal alpha should be available latest 2 weeks before M2 (05-31)
alpha release PR targeted by June 7. M1 target 06-15 
M2 (Commonalities & ICM)06-15

propose to shift by 1 month to 07-15
M3 (Sub Projects)07-15

May be earlier :-)
M4 (Sub Projects)08-30


M509-15


M609-30


...