Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 04-15 | kick-off done | 2024-04-18 |
|
M1 (Commonalities & ICM) | alpha PRfinal alpha should be available latest 2 weeks before M2 (05-31) | alpha release PR targeted by June 7. M1 target 06-15 | ||
M2 (Commonalities & ICM) | 06-15 | propose to shift by 1 month to 07-15 | ||
M3 (Sub Projects) | 07-15 | May be earlier :-) | ||
M4 (Sub Projects) | 08-30 | |||
M5 | 09-15 | |||
M6 | 09-30 |
...