Timeline
Milestone dates
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 04-15 | kick-off done | 2024-04-18 |
|
M1 (Commonalities & ICM) | alpha PR | final alpha should be available latest 2 weeks before M2 | ||
M2 (Commonalities & ICM) | 06-0715 | |||
M3 (API Sub-projects) | 06-2115 | |||
M4 (API Sub-projects) | 08-30 | |||
M5 | 09-15 | |||
M6 | 09-30 |
...