- M0: was approved on 2024-04-18, but announcement still needs to be sent. Check draft M0 announcement here: Release Management announcements - sending of the M0 announcement is dependent on the finalization of the API release tracker page.
- M1: Proposal to shift by 2 weeks to 2024-05-15, but this is maybe not sufficient as holidays in many countries. Means one month delay wrt standard schedule.
- M2 will most propbabli likely also shift shift by 2 weeks
- M3: shifts with the M1 date
- Other milestones: no change
- API Sub-projects should start to prepare the release assets for their APIs for release and align with Commonalities and ICM AS OF TODAY. When can an alpha release for Commonalities & ICM be created ?
- In the general meta-release schedules: moved M2 one week earlier and M3 one week later.
- Process definition status:
- Updates the milestone table with new format and clarified actions - near final
- Update of process descriptions near final;
- API readiness checklist to be finalized.