Release Management (Tanja de Groot Samuel Adeyemo )

  • Initial content:
    • M0: was approved on 2024-04-18, but announcement still needs to be sent. Check draft M0 announcement here
    • M1: Proposal to shift by 2 weeks to 2024-05-15, but this is maybe not sufficient as holidays in many countries. .
    Discussion...
    • Means one month delay wrt standard schedule.
    • M2 will most propbabli also shift  by 2 weeks
    • M3: shifts with the M1 date
    • Other milestones: no change
    • API Sub-projects should start to prepare the release assets for their APIs for release and align with Commonalities and ICM AS OF TODAY. When can an alpha release for Commonalities & ICM be created ?
    • In the general meta-release schedules: moved M2 one week earlier and M3 one week later.
    • Process definition status:
      • Updates the milestone table with new format and clarified actions - near final
      • Update of process descriptions near final;
      • API readiness checklist to be finalized.
  • Discussion:

Sub Project Lifecycle proposals (Herbert Damker )

...