Timeline
Milestone dates
Milestone | Target date | Status | Actual date |
---|---|---|---|
M0 | 04-15 | kick-off done | 2024-04-18 |
M1 (Commonalities & ICM) | 04-30 | alpha preparation | |
M2 (Commonalities & ICM) | 06-15 | ||
M3 (API Sub-projects) | 06-15 | ||
M4 (API Sub-projects) | 08-30 | ||
M5 | 09-15 | ||
M6 | 09-30 |