WIP
Introduction
The purpose of this document is to describe the cadence, processes, milestones, and associated tasks used in the CAMARA release cycle. See CAMARA Releases for information and schedule for specific releases.
Overview
CAMARA releases is scheduled to twice per year at approximately 6 month intervals (May and November). Releases are named after major world cities in alphabetical order. See the CAMARA Release Roadmap for a list of previous and future releases.
Releases are administered and tracked by a Community Release Managers. Release status is discussed at the << TBC >>
Release Milestones
Release milestones and their associated tasks, are used to track the status of the release. The milestones and management tasks used in the release process are described in the table below.
Milestone | Milestone Name | Description | Timeline |
---|---|---|---|
Kickoff - M0 | Start of release cycle. | M0 | |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week |
M2 | Finalize Commonalities & ICM |
| M1 + 7 weeks |
M3 | Initiate Sub-Projects / APIs |
| M1 + 6 weeks |
M4 | Finalize Sub-projects / APIs |
| M3 + 8 weeks |
M5 | Meta Release |
| M4 + 2 weeks |
M6 | Post- Release |
| M5 + 2 weeks |
....................................