Milestone | Description | Timeline |
---|---|---|
Kickoff - M0 | Start of release cycle. | M0 |
Initiate Commonalities & ICM - M1 | Scope of Work Products clarified. | M0 + 1 week |
- Identify commonalities among work products. | ||
- Gather requirements for commonalities. | ||
- Create initial PRs for commonalities. | ||
- Complete initial PR reviews. | ||
- Agree on the scope of commonalities. | ||
- Select release candidates for commonalities. | ||
TSC Approval. | ||
Finalize Commonalities & ICM - M2 | Release of Commonalities. | M1 + 4 weeks |
TSC Approval. | ||
Initiate Sub-Projects / APIs - M3 | Scope Request to Sub-Projects / APIs. | M1 + 6 weeks |
- Determine requirements for sub-projects/APIs. | ||
- Create PRs for sub-projects/APIs. | ||
- Review and finalize PRs. | ||
- Confirm scope of sub-projects/APIs. | ||
- Identify release candidates for sub-projects/APIs. | ||
Finalize Sub-projects / APIs - M4 | Release of Sub-Projects / APIs. | M3 + 2 weeks |
Meta Release | Testing & Acceptance. | M4 + 8 weeks |
- Conduct testing. | ||
- Evaluate acceptance criteria. | ||
Release Retro. | ||
- Review release process and identify areas for improvement. | ||
TSC Approval. | ||
Bundle & publish release - Common Release Date ("packaging done for the community release"). |
...