MilestoneDescriptionTimeline
Kickoff - M0Start of release cycle.M0
Initiate Commonalities & ICM - M1Scope of Work Products clarified.M0 + 1 week

- Identify commonalities among work products.

- Gather requirements for commonalities.

- Create initial PRs for commonalities.

- Complete initial PR reviews.

- Agree on the scope of commonalities.

- Select release candidates for commonalities.

TSC Approval.
Finalize Commonalities & ICM - M2Release of Commonalities.M1 + 4 weeks

TSC Approval.
Initiate Sub-Projects / APIs - M3Scope Request to Sub-Projects / APIs.M1 + 6 weeks

- Determine requirements for sub-projects/APIs.

- Create PRs for sub-projects/APIs.

- Review and finalize PRs.

- Confirm scope of sub-projects/APIs.

- Identify release candidates for sub-projects/APIs.
Finalize Sub-projects / APIs - M4Release of Sub-Projects / APIs.M3 + 2 weeks
Meta ReleaseTesting & Acceptance.M4 + 8 weeks

- Conduct testing.

- Evaluate acceptance criteria.

Release Retro.

- Review release process and identify areas for improvement.

TSC Approval.

Bundle & publish release

- Common Release Date ("packaging done for the community release").


...