Milestone / start date

Actors & Activities for next milestone

Timeline

Week Nr

pre-M0 activities
  • Release Management: prepare meta-release plan
  • Commonalities & ICM: define scope and start alpha release development
  • TSC: declare M0 - meta-release kickoff


M0 

Meta-release kickoff

M00
starts activities for M1 start @ M0
  • Commonalities & ICM: fix scope and develop final alpha release for M1
  • API Sub Groups: check Commonalities and ICM scope definition to assess API impact
  • TSC: approve Commonalities and ICM scope and final alpha release
  • Release Management: Declare M1 - Commonalities and ICM alpha release available
2 weeks

M1

Alpha Commonalities & ICMM0 + 2 weeks2
starts activities for M2 start @ M1
  • API Sub Groups: align to Commonalities and ICM alpha release and provide feedback
  • Commonalities & ICM: Fix bugs and prepare final release-candidate for M2
  • TSC: approve Commonalities and ICM final release-candidate
  • Release Management; declare M2 - Commonalities and ICM release-candidate available
7 weeks

M2

Release-candidate Commonalities & ICMM1 + 7 weeks9
starts activities for M3 start @ M1
  • API Sub Projects: prepare API scope and develop alpha releases, ending by the first release-candidate for M3
  • TSC: review scope of APIs (case by case selection)
  • Release Management: check API readiness of each API and declare M3 - all API first release-candidates available
9 weeks

M3

Release-candidate APIs (Code Freeze)

M1 + 9 weeks

9
starts activities for M4 start @ M3
  • API Sub Projects: fix bugs and prepare public-release
  • Commonalities & ICM: prepare public-release
  • Release Management: check API readiness of each API and declare M4 - all API public-releases available
  • TSC: give formal approval of Commonalities, ICM and API (case-by-case) public-releases
9 weeks

M4

Public-release APIs

M3 + 9 weeks

18

activities for M5 starts @ public-release PR for an API

  • Release Management: prepare and declare M5 - meta-release availability
  • TSC: approve meta-release for M5
2 weeks

M5

Meta-releaseM4 + 2 weeks20
starts activities for M6 start @ M5
  • Commonalities & ICM: assess meta-release and provide feedback
  • API Sub Groups: assess meta-release and provide feedback
  • Release Management: assess meta-release, create improvement plan and declare M6 - post-release assessment available
  • TSC: approve improvement plan for M6
2 weeks

M6

Post Release AssessmentM5 + 2 weeks24

...