- Commonalities, ICM: release tracking and milestone activities
- API Sub Projects: release tracking and milestone activities
- Release Management: meta-release tracking and milestone activities
- TSC: milestone activities
Milestone / start date | Actors & |
---|
Activities for next milestone | Timeline | Week Nr |
---|---|---|
pre-M0 |
|
|
|
- Starting from previous M2, prepare scope definition for upcoming meta-release.
- Implement scope in one or more alpha releases
TSC
|
| |||
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 |
- Announce M0 meta-release kick-off on all@lists.camaraproject.org
- Once available, check the final alpha releases PR of Commonalities & ICM and, if OK, submit to TSC for approval
- After TSC approval, announce M1 milestone
Commonalities & ICM
- Finalize the scope definition for meta-release.
- Record scope in dedicated GitHub issue.
- Submit scope issue for TSC review
- Develop final Commonalities & ICM scope through one or more alpha releases
- Update data in the meta-release plan with each alpha release
- Create final alpha release PRs and submit to Release Management
- After TSC approval, create approved final alpha release for Commonalities & ICM
- Update the meta-release plan with the alpha release tag
API Sub Projects
- Start following the scope definitions of Commonalities and ICM and assess impact on API version
TSC
|
2 weeks | |||
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 |
|
|
- Create the final release-candidate for Commonalities & ICM
- Update the meta-release page for Commonalities & ICM with release-candidate tag
Release Management
- Check final release-candidate PRs of Commonalities and ICM and, if OK, submit to TSC for approval
- After TSC approval, and commit of Commonalities and ICM final release-candidate PRs, announce M2 milestone
TSC
- Approve final release-candidate PRs of Commonalities & ICM
| 7 weeks | ||
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 |
|
- Create API release tracking page for the API if it does not yet exist
- Create API release tracker for the API version to be released
- Assess final impact of final release-candidates of Commonalities and ICM scope on API(s)
- Define scope of API release:
- Record scope in dedicated GitHub issue.
- Update the release tracker with the scope issue link
- Develop API scope through one or more alpha releases
- Update the API release tracker with each alpha release
- Create first release-candidate PR and submit to Release Management
- After Release Management approval:
- Create first release-candidate for the API
- Update the API release tracker with the release-candidate tag
Release Management, for each API
- Once available, check the first API release-candidate PR and, if OK, approve PR
- Announce M3 milestone with all approved API release-candidates.
TSC
- Review scope of selected APIs (case by case selection)
| 9 weeks | ||
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 |
|
- Fix bugs raised by API testers through one or more release-candidates
- Update API release tracker with each release-candidate
- Submit final release-candidate PR to Release Management for checking
- After final release-candidate PR approval by Release Management:
- Create final release-candidate and update API release tracker
- Create API public-release PR
- After TSC approval of the PR
- Create public-release
- Update the API release tracker with public-release tag
Release Management, for each API
- Once available, check final API release-candidate PR and, if OK, approve PR
- Once available, check API public-release PR, and, if OK, ask for formal TSC approval.
- Announce M4 milestone when all API public-releases are approved by TSC
Commonalities & ICM (through M3 upto M4)
- Fix bugs raised by API testers through one or more release-candidates
- Create public-release PR for Commonalities & ICM
- After Release Management check and TSC approval of the public-release PR
- Create the public-release
- Update the meta-release page with public-release tag
TSC
|
9 weeks | |||
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API |
|
|
|
|
TSC:
- Meta-release approval
|
2 weeks | |||
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 |
Release Management
- Review release process with all teams and identify areas for improvement.
- Propose improvements for TSC approval
- After TSC approval, announce M6 milestone
TSC
|
2 weeks | |||
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
Processes
All CAMARA teams play their part in the meta-release process. The actions are listed in the above milestone table.
...