- the milestones of the meta-release (this page), and the supporting Meta-release Process documentation
- the activities expected from the different teams to move from one milestone to another, with details documented here:the next
- the way to report progress on the meta-release itself, on the Commonalities and ICM releases and on API releases is also part of the above process descriptions.
...
- A meta-release has 6 milestones, M0 through M6 described below.
- For the typical milestone dates of a meta-release, please see the Meta-release Process.
The actions following table lists the meta-release milestones, and includes a high level view of the activities expected from the various teams to reach the milestones are described in the table below. More details on the actions can be found in Meta-release Process and the API Release Process descriptions.NOTE: Deviations from the below actions or timeline are to be documented on the dedicated meta-release plan. For example, see here for the Meta-release Fall24.these milestones.
More details on these for each team are documented here:
Milestone / start date | Actors & Actions for next milestone | Timeline | Week Nr |
---|
pre-M0 | Release Management - Prepare meta-release page
- Request TSC to declare kickoff
Commonalities & ICM - Starting from previous M2, prepare scope definition for upcoming meta-release.
- Implement scope in one or more alpha releases
TSC - Declare meta-release kickoff
|
|
|
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | Release Management - Announce M0 meta-release kick-off on all@lists.camaraproject.org
- Once available, check the final alpha releases PR of Commonalities & ICM and, if OK, submit to TSC for approval
- After TSC approval, announce M1 milestone
Commonalities & ICM - Finalize the scope definition for meta-release.
- Record scope in dedicated GitHub issue.
- Submit scope issue for TSC review
- Develop final Commonalities & ICM scope through one or more alpha releases
- Update data in the meta-release plan with each alpha release
- Create final alpha release PRs and submit to Release Management
- After TSC approval, create approved final alpha release for Commonalities & ICM
- Update the meta-release plan with the alpha release tag
API Sub Projects - Start following the scope definitions of Commonalities and ICM and assess impact on API version
TSC - Approve Commonalities and ICM scope
- Approve final alpha release PRs of Commonalities & ICM
| 2 weeks |
|
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | Commonalities & ICM - Fix bugs raised by users through one or more release-candidates
- Update release tracker on meta-release page with each release-candidate
- Create final release-candidate PR and submit to Release Management
- After TSC approval:
- Create the final release-candidate for Commonalities & ICM
- Update the meta-release page for Commonalities & ICM with release-candidate tag
Release Management - Check final release-candidate PRs of Commonalities and ICM and, if OK, submit to TSC for approval
- After TSC approval, and commit of Commonalities and ICM final release-candidate PRs, announce M2 milestone
TSC - Approve final release-candidate PRs of Commonalities & ICM
| 7 weeks |
|
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 | API Sub Projects - Create API release tracking page for the API if it does not yet exist
- Create API release tracker for the API version to be released
- Assess final impact of final release-candidates of Commonalities and ICM scope on API(s)
- Define scope of API release:
- Record scope in dedicated GitHub issue.
- Update the release tracker with the scope issue link
- Develop API scope through one or more alpha releases
- Update the API release tracker with each alpha release
- Create first release-candidate PR and submit to Release Management
- After Release Management approval:
- Create first release-candidate for the API
- Update the API release tracker with the release-candidate tag
Release Management, for each API - Once available, check the first API release-candidate PR and, if OK, approve PR
- Announce M3 milestone with all approved API release-candidates.
TSC - Review scope of selected APIs (case by case selection)
| 9 weeks |
|
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 | API Sub Projects - Fix bugs raised by API testers through one or more release-candidates
- Update API release tracker with each release-candidate
- Submit final release-candidate PR to Release Management for checking
- After final release-candidate PR approval by Release Management:
- Create final release-candidate and update API release tracker
- Create API public-release PR
- After TSC approval of the PR
- Create public-release
- Update the API release tracker with public-release tag
Release Management, for each API - Once available, check final API release-candidate PR and, if OK, approve PR
- Once available, check API public-release PR, and, if OK, ask for formal TSC approval.
- Announce M4 milestone when all API public-releases are approved by TSC
Commonalities & ICM (through M3 upto M4) - Fix bugs raised by API testers through one or more release-candidates
- Create public-release PR for Commonalities & ICM
- After Release Management check and TSC approval of the public-release PR
- Create the public-release
- Update the meta-release page with public-release tag
TSC - Formal approval of the Commonalities & ICM public-release PRs
- Formal approval API public-release PRs
| 9 weeks |
|
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API | Release Management - Check that all API release trackers are updated with their public-release tag for the meta-release.
- Propose meta-release content to TSC
- After TSC approval, publish the meta-release
- Announce the M5 meta-release on all@lists.camaraproject.org
TSC: | 2 weeks |
|
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 | Release Management - Review release process with all teams and identify areas for improvement.
- Propose improvements for TSC approval
- After TSC approval, announce M6 milestone
TSC - Provide feedback on meta-release
- Meta-release improvements approval.
| 2 weeks |
|
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
...