The purpose of this document is to describe the milestones and expected tasks. It references the supporting processes used in the CAMARA meta-release cycle.actions by the different teams. 

For the schedule and content of planned meta-releases, see CAMARA meta-releases.

Meta-release Milestones

Meta-release milestones and their associated actions are used to progress and track the status of the meta-release. 

  • A meta-release has 6 milestones, M0 through M6 described below. 
  • For the typical milestone dates of a meta-release, please see

...

Release milestones and their associated actions are used to progress and track the status of the meta-release.

The actions required expected from the various teams in to reach the release process milestones are described in the table below. More information details on the actions can be found in the Meta-release Process description and the API Release Process descriptions.

NOTE: Deviations from the below actions or timeline is to be documented on the dedicated meta-release pages, in particular for the Meta-release Fall24.

...