A meta-release cycle covers 6 7 milestones, M0 through M6. The below figures provide the typical planning and milestone dates for a Spring or Fall meta-release.

Actual dates for a given meta-release shall be managed on the dedicate meta-release plan which are listed here: CAMARA meta-releases.

...

The following actions are requested from the various teams to plan and provide visibility on the progress of a meta-release. They are also listed in the milestone table.

NOTE: in case of differences between this page and the milestone table, or in case of missing points or proposed changes or other feedback, please use the Meta-release retrospective page.

Release Management

The Release Management team shall create the meta-release plan (page) under CAMARA meta-releases as follows:

...