WIP
Table of Contents |
---|
Introduction
The purpose of this document is to describe the cadence, processes, milestones, and associated tasks used in the CAMARA meta-release cycle.
See CAMARA meta-releases for information and schedule of planned meta-releases.
Meta-release Milestones
A meta-release has 6 milestones, M0 through M6 described below. For the typical milestone dates of a meta-release, please see the Meta-Release Planning.
...
Milestone | Milestone Name | Actions to achieve milestone | Timeline | Week number |
---|---|---|---|---|
Kickoff - M0 | Start of meta-release cycle. | M0 | 0 | |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week | 2 |
M2 | Finalize Commonalities & ICM |
| M1 + 10 weeks | 12 |
M3 | Initiate Sub-projects / APIs |
| M1 + 8 weeks | 10 |
M4 | Finalize Sub-projects / APIs |
| M3 + 10 weeks | 20 |
M5 | Meta Release |
| M4 + 2 weeks | 22 |
M6 | Post- Release |
| M5 + 2 weeks | 24 |
Release cadence
CAMARA meta-releases are scheduled twice per year at approximately 6 month intervals (March and September).
Meta-releases are named SpringYY or FallYY respectively, where YY is the (short) year number. For example Fall24, Spring25, Fall25, etc.
Release contacts
Meta-releases are administered and tracked by
...
Team release contacts need to subscribe to the release management mailing list.
Processes
All CAMARA teams play their part in the meta-release process. This section describes the action of each team.
...