Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Release milestones and their associated tasks, are used to track the status of the meta-release. The milestones and management tasks used in the release process are described in the table below.

MilestoneMilestone NameDescriptionActions to achieve milestoneTimeline


Timeline

update

Week number

Kickoff - M0Start of release cycle.
M0
M00







M1

Initiate Commonalities & ICM
  • Scope of Work Products clarified  and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities and ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.
M0 + 2 week
M0 + 2 week2




M2

Finalize Commonalities & ICM
  • Create release-candidate for Commonalities and ICM
  • Prepare public-release for Commonalities & ICM.
  • Complete initial PR reviews.
  • TSC Approval.
M1 + 7 weeks
M1 + 8 (+2) weeks12








M3

Initiate Sub-Projects / APIs
  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for Sub-projects / APIs.
  • Create PRs for Sub-projects / APIs.
  • Review and finalize PRs.
  • Confirm scope of Sub-projects / APIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Create alpha release for for Sub-projects / APIs.
M1 + 6 weeks
M1 + 6 (+2) weeks10







 M4

M4

Finalize Sub-projects / APIs
  • Conduct testing and log test result.
  • Evaluate and log acceptance criteria.
  • Code Freeze
  • Create release-candidate for Sub-Projects / APIs.
  • Prepare public-release for Sub-Projects / APIs.
  • Request approval of Sub-projects / APIs to Release Management WG for meta-release
M3 + 8 (+2) weeks
M3 + 8 (+2) weeks20




M5

Meta Release
  • Determine the acceptance of the release-candidates for inclusion in the meta-release
  • Bundle & publish meta-release
  • TSC Approval
  • Publish meta-release
M4 + 2 weeks
M4 + 2 weeks22



M6

Post- Release
  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.
M5 + 2 weeks
M5 + 2 weeks24

...