MilestoneMilestone NameDescriptionTimeline


Timeline

update

Week number

Kickoff - M0Start of release cycle.
M0
M00
M1Initiate Commonalities & ICM
  • Scope of Work Products clarified.
  • Identify commonalities work products.
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC Approval.
M0 + 2 week
M0 + 2 week2
M2Finalize Commonalities & ICM
  • Release of Commonalities.
  • Complete initial PR reviews.
  • TSC Approval.
M1 + 7 weeks
M1 + 8 (+2) weeks12
M3Initiate Sub-Projects / APIs
  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for sub-projects/APIs.
  • Determine requirements for sub-projects/APIs.
  • Create PRs for sub-projects/APIs.
  • Review and finalize PRs.
  • Confirm scope of sub-projects/APIsAPIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Identify release candidates for sub-projects/APIs.
M1 + 6 weeks
M1 + 6 (+2) weeks10
 M4Finalize Sub-projects / APIsRelease of Sub-Projects / APIs.Testing & Acceptance.
  • Conduct testing.
  • Evaluate acceptance criteria.
  • Code Freeze
  • Create release candidate of Sub-Projects / APIs.
  • Submit RC to release management WG for Meta Release
M3 + 8 (+2) weeks
M3 + 8 (+2) weeks20
M5Meta Release
  • Determine the acceptance of the RC for Meta Release
  • Bundle & publish release
  • Common Release Date ("packaging done for the community release").
M4 + 2 weeks
M4 + 2 weeks22
M6Post- Release
  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.
M5 + 2 weeks
M5 + 2 weeks24

...