The purpose of this document is to describe the cadence, processes, milestones, and associated tasks used in the CAMARA release cycle. See CAMARA meta-releases for information and schedule for specific releases.

...

Process

CAMARA meta-releases is are scheduled to twice per year at approximately 6 month intervals (May March and NovemberSeptember). Releases Meta-releases are named after major world cities in alphabetical order. See the CAMARA Release Roadmap for a list of previous and future releases..

Meta-release have 6 milestones, M0 through M6 described below. For the milestone dates per meta-release, please see the CAMARA Release Roadmap.

Meta-releases Releases are administered and tracked by a Community Release Managers. Release status is discussed at the << TBC >>

  • the CAMARA Release Managers, supported by
  • the release contacts of the Commonalities and ICM working groups 
  • the release contacts of the API Sub-projects

The teams can put their release contact names on the Sub-project Release Contacts (Maintainers) page.

The ongoing meta-release status is discussed in the Release Management working group meetings and recorded on the meta-release page.

Release Milestones

Release milestones and their associated tasks, are used to track the status of the meta-release. The milestones and management tasks used in the release process are described in the table below.

MilestoneMilestone NameDescriptionTimeline


Timeline

update

Week nr

Kickoff - M0Start of release cycle.
M0
M00
M1Initiate Commonalities & ICM
  • Scope of Work Products clarified.
  • Identify commonalities work products.
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC Approval.
M0 + 2 week
M0 + 2 week2
M2Finalize Commonalities & ICM
  • Release of Commonalities.
  • Complete initial PR reviews.
  • TSC Approval.
M1 + 7 weeks
M1 + 8 (+2) weeks12
M3Initiate Sub-Projects / APIs
  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for sub-projects/APIs.
  • Determine requirements for sub-projects/APIs.
  • Create PRs for sub-projects/APIs.
  • Review and finalize PRs.
  • Confirm scope of sub-projects/APIs.
  • Identify release candidates for sub-projects/APIs.
M1 + 6 weeks
M1 + 6 (+2) weeks10
 M4Finalize Sub-projects / APIs
  • Release of Sub-Projects / APIs.
  • Testing & Acceptance.
  • Conduct testing.
  • Evaluate acceptance criteria.
  • Code Freeze
M3 + 8 (+2) weeks
M3 + 8 (+2) weeks20
M5Meta Release
  • Bundle & publish release
  • Common Release Date ("packaging done for the community release").
M4 + 2 weeks
M4 + 2 weeks22
M6Post- Release
  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.
M5 + 2 weeks
M5 + 2 weeks24

Meta-release content planning

...