Milestone | Milestone Name | Description | Timeline |
---|---|---|---|
Kickoff - M0 | Start of release cycle. | M0 | |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week |
M2 | Finalize Commonalities & ICM |
| M1 + 7 weeks |
M3 | Initiate Sub-Projects / APIs |
| M1 + 6 weeks |
M4 | Finalize Sub-projects / APIs |
| M3 + 8 weeks |
M5 | Meta Release |
| M4 + 2 weeks |
M6 | Post- Release |
| M5 + 2 weeks |
...
Meta-release content planning
For each meta-release, the respective teams shall update the information of what they plan to contribute on the relevant meta-release page.
Commonalities & ICM
The Commonalities and ICM teams shall respectively update the related table as follows:
- The version shall be updated with the latest pre-release version in use by the respective teams.
- The actual Mx dates shall be put in the table when the milestone is passed.
- The link to the release package shall be added at M2 and is the same at M5.
- When M2 is passed, the target public-release version shall be put in the Version column.
APIs
API Sub-project teams shall update the table for APIs as follows:
- The version shall be updated with the latest pre-release API version in use by the team.
- The actual Mx dates shall be put in the table when the milestone is passed.
- The link to the release package shall be added at M3, M4, and the final at M5.
- When M5 is passed, the target public-release API version shall be put in the Version column.